一、传输线路光缆
A cable, transmission lines
1 挂钩规格:25mm 、35mm ; 光揽挂钩的间距应为50cm,允许偏差+-3cm。电杆两侧第一个挂钩应距离杆25cm,允许偏差+-2cm
1 link specification: 25 mm, 35 mm; Light pull hook spacing should be 50 cm, allowable deviation + 3 cm. On both sides of the pole should be the first hook rod 25 cm and allowable deviation + - 2 cm
2 跨公路时需挂光缆警示牌
2 needing hung cable across the road sign
3 每5根杆档处做一处弯曲预留(小预留,25-30cm),预留光缆需用15mm塑料波纹管保护,每10根作一处大预留,长度约12-15米
3 every 5 make a curved root pole shift in reserve (small reserve, 25 to 30 cm), the reserved cable need 15 mm plastic corrugated pipe protection, every 10 root as a big reserve, about 12 to 15 meters length
4 光缆接头盒离电杆的距离约60cm,接头盒两端光缆需做大预留
4 cable connector box is about 60 cm from the distance of the pole, connector box on both ends of the cable has to be reserved
5 电杆洞深,偏差应小于5cm
5 pole hole deep, deviation should be less than 5 cm
6 电杆杆距:市区 35-40米,郊区 45-50 米
6 pole pole: from urban 35-40 meters, suburban 45 to 50 meters
7 竖立电杆:
7 erect pole:
1)直线线路,电杆中心线的偏差应不大于5cm,电杆本身应上下垂直
1) straight line, the center line of the electric pole of deviation should be no greater than 5 cm, the pole itself should be vertically up and down
2)转角杆:应在线路转角内移10-15cm,只能外倒不能内扑
2) Angle pole: should be in line Angle within 10 to 15 cm, can only pour can't jump
3)终端杆竖立后应向拉线倒,倾斜10-20cm
3) terminal should be to pull down after stem erect, tilt 10-20 cm
4)电杆喷号:最末一字或杆号牌下边字迹距地面2.5m,杆号应面向公路;喷字内容:移动标志、杆路建设年,A-B端基站的简称、电杆顺序号
4) spray pole number: at the end of a word or the bottom of the pole plate handwriting is apart from the ground 2.5 m, pole number should be geared to the needs of the highway; Spray word content: mobile logo, bar in road construction, short for base station, A - B end pole serial number
8 拉线
Eight arrows
1)角杆拉线常用7/2.6镀锌钢绞线,这种钢绞线的机械强度最小拉断力约4100公斤
1) Angle bar pull 7/2.6 commonly used galvanized steel wire, the steel strand the mechanical strength of minimum tensile force of about 4100 kg
2)拉线扎固方式有:另缠法、夹板法、卡固法三种;拉线有上把、中把之分
2) stay compaction methods are: the other bound method, plywood, card solid three; Arrows can be put, put
拉线另缠法,中把:首节15cm--间隔28公分--钢线留长10公分--间隔—1.6钢绞线5圈
Pull the other bound method, the: the first section 15 cm - 28 cm intervals - steel wire to keep long 10 cm - 1.6 - interval steel strand five laps
上把:首节15cm--间隔3公分--钢线留长10公分--间隔—1.6钢绞线5圈
Up: the first section 15 cm - 3 cm between steel wire to keep long 10 cm - 1.6 - interval steel strand five laps
3)靠近高压电力设施及热闹市区的拉线,根据设计规定加绝缘子(绝缘子离地面距离应在2M以上,行人道上的拉线要加套竹筒保护,并刷红白反光油漆
3) stay near the high voltage electric power facilities and lively city, according to the design rules and insulator (insulator should be more than 2 m above the ground distance, the sidewalk thread to jacketed to spill protection, and red and white reflective paint
转角杆单条拉线抱箍装在吊线夹板之上10cm处,双方向拉线抱箍装在吊线之下40cm处
Corner pole a single thread hoop in a messenger wire splint above 10 cm, both sides to pull embrace hoop is installed under the messenger wire 40 cm
4)地锚块尺寸为60*40*15cm,地锚点出土偏差要小于5cm,地锚坑的深度比杆洞深10cm左右(拉线衬环出土60cm,误差不大于5cm)
4) anchor block size 40 to 60 * * 15 cm, anchor point deviation is less than 5 cm, unearthed from the depth of the ground anchor pit than stem hole deep 10 cm (pull ring unearthed 60 cm, the error is not more than 5 cm)
拉线种类:1、落地拉线2、高拉桩拉线3、吊板拉线4、V型拉线5、地桩拉线(用于化学严重腐蚀的地区)6、杆间拉线(由于相邻杆档的间载荷不同或杆距不同,有受地理限制采用的)7、撑杆(受地形限制,无法装设拉线时)
Pull type: 1, the ground wire 2, 3 high pile anchor, hanger stay 4, v-shaped stay 5, to pile anchor (used in chemical severe corrosion area) 6, between anchor rod (due to the different load or between adjacent pole shift lever from is different, have restricted by geographical adopt) 7, poles (restricted by terrain, unable to furnish arrows)
9 吊线
9 messenger wire
1)一般比拉线程式降低一级,用7/2.2镀锌钢绞线,每盘2公里长,机械强度最小拉断力为2940公斤;辅助吊线有用到7/3.0钢绞线,机械强度最小拉断力为5460公斤
1) general lower level than pull a program, with 7/2.2 of galvanized steel wire, each coil 2 kilometers long and mechanical strength of minimum tensile force of 2940 kg; Auxiliary suspension wire useful to 7/3.0 steel strand, mechanical strength of minimum tensile force is 5460 kg
2)吊线之间连接需用蛋形隔电子(规格5吨)
2) suspension wire connection between need egg every electronic specifications (5 tons)
3)吊线每公里需做直埋式接地连接
3) messenger wire per kilometre to do direct buried grounding connection
4)吊线安装位置,距末梢不小于60cm,特殊情况下不小于25cm
4) messenger wire installation location, is apart from the peripheral is not less than 60 cm, special circumstances should not less than 25 cm
5)如果杆路上需上下敷设两条吊线,吊线间距应为40cm
5) if the lever need two messenger wire laying up and down on the road, messenger wire spacing should be 40 cm
6)吊线与其他建筑物最小垂直净距
6) messenger wire net minimum vertical distance and other buildings
市区街道:5.5m 公路:5.5m 土路:4.5m 树木:1m 通信线路:0.6m
Downtown streets: 5.5 m roads: 5.5 m dirt road: 4.5 m trees: 1 m communication lines: 0.6 m
7)当相邻的杆高度差在2.5-5m时,需加装吊线仰俯角辅助装置
7) when the adjacent pole height difference in 2.5 5 m, need to add messenger wire back bow Angle auxiliary device
8)当夹角在145-168度时,外角杆需加装吊线辅助装置
8) when in 145-168 degree Angle, outside, messenger wire rod should be mounted to the assist device
9)吊线在终端杆及角深大于15米(夹角小于145度)时,应做终结
9) disconnect the terminal bar and Angle is greater than 15 meters (less than 145 degree Angle), should be an end